The 2013 School Investment Program included renovations to 98 Chicago Public School facilities. The Blinderman design-build team was awarded Package #2, which required the design-build renovation of three public school facilities – Lincoln Park Highschool, Marshall Middle School, and Northwest Middle School – all to be completed under an aggressive, phased schedule.
The Blinderman team successfully designed, engineered and safely constructed over $14M in renovations at the three scattered sites over a single 6-week period – exceeding a significant minority and woman owned business participation requirements at the prime builder and design lead levels, and owner quality expectations.
Varying scopes to add or upgrade a range of amenities at the schools included:
3 sites in Chicago: Lincoln Park High School, Marshall Middle School, NOrthwest Middle School
Chicago Public Building Commission
$14M
Complex Renovation
Design-Build